Planned projects

Construction of the 330 MW second phase of the combined cycle gas turbine power plant (CCGT PP), comprising two 165 MW combined cycle gas units (CCGT-165)

Project scope

Construction of the 330 MW second phase of the combined cycle gas turbine power plant (CCGT PP), comprising two 165 MW combined cycle gas units (CCGT-165)

Source of financing

Own and borrowed funds

Implementation period

July 2026 – April 2030

Current status

At the feasibility study development stage

   

Expansion of a steam-gas turbine power plant for the construction of an additional 165 MW power unit

The project consists

of 2 gas turbine generators (50 MW) and 1 steam turbine generator (65 MW)

Source of funding:

at the stage of determination, the EBRD and EDB have shown interest in financing the Project. Debt financing is being worked out through the K-SURE South Korean ECA.

Implementation period:

2023-2027

Current status:

consideration of the Project concept

   

Construction of infrastructure facilities in the SEZ NIPT (2nd stage) for the needs of the "Polyethylene" Projects

The project consists

of 220 kV overhead line with a length of 58 km

Source of funding:

Republican Budget

Implementation period:

2025-2027

Current status:

passing corporate procedures, development of project documentation

   

Waste processing complex with water treatment and wastewater treatment plant

The project consists

of waste recycling plant

Source of funding:

Own funds

Implementation period:

2023-2026

Current status:

passing corporate procedures

   

Construction of a technical water pipeline from Atyrau to Karabatan

The project consists

of 31 km long water pipeline

Source of funding:

is under consideration

Implementation period:

2023-2024

Current status:

a memorandum of the project is being worked out jointly with the Akimat of Atyrau region