Karabatan Utility Solutions LLP announces the commencement of works on

1. Modernisation and reconstruction of the ZLD plant:

- Repair and modernisation of technological equipment;

- Construction of a new workshop for the zero liquid discharge system installation.

The plant is designed for deep processing of mineralised wastewater and concentrate from the first stage reverse osmosis plant, which is formed in the process of desalination of source water, which is a mixture of treated wastewater and river water.

The work implementation plan is scheduled for 2025-2026.

2. Reconstruction of the sewage receiving system and modernisation of manholes.

The work implementation plan is scheduled for 2025-2027.

Additional information can be obtained from 08:30 to 17:30 on March 14, 2025 by phone 8 (7122) 763660 (ext.445), by e-mail: zhabasova@kus.com.kz, as well as by official email: info@kus.com.kz.