Construction of 2 lines of overhead line 220 for the needs of KEGOC JSC (41 km.)

The project consists

of 2 220 kV overhead lines with a length of 41 km

Source of funding:

Samruk-Kazyna loan

Commissioning date:

July 2019

Physical progress:

100%

Current status:

implemented in favor of KEGOC JSC